Project Brief
Regional Electronic Cargo Tracking Northern Corridor – RECTS
Implementation Partners
--
Implementation Period
2018 - 2021
Project Participants
--
Project Value
$ 800,000
Project Rationale
TMA is supporting DRC Customs Administration – DGDA introducing an electronic cargo tracking system on Northern Corridor to reduce transit-related costs by reducing transit time; reducing physical inspections by customs transactions due to reduced risks.
NB/ If the project is above $250,000 a PAR must be submitted for approval
Project Approval Summary:
Responsibility Center: 22_DRC
- PAR approval date: June 2016
- PAR number: DRC CBT PAR
- PAR approval authority: Board