Taveta KE / Holili TZ

Home > OSBP
  • Taveta KE
  • Holili TZ

LOCATION

The Taveta/Holili border crossing point between Southern Kenya and Northern Tanzania is located about 264 km SouthEast of Mombasa and 110 km West of Arusha. The Kenyan side of the border is in Taita-Taveta County, while the Tanzanian side is in Himo Town, Rombo District, Kilimanjaro Region. Taveta is one of the key border crossing points between the two countries due to the border’s proximity to major cities.

WHY

To transport goods to Arusha and surrounds in northern Tanzania, vehicles currently must pass through the Namanga border. This route is considerably longer than the Taveta/Holili route. Operationalising the Taveta/Holili border is expected to increase with the construction of a new Voi-Arusha road passing through the two border points, stretching the capacity of the current infrastructure and operations and increase waiting time for import and export processing. Increased delays create costs for traders.

  • IMPLEMENTING PARTNER

    Kenya Revenue Authority
  • RESULTS

    Baseline Data

    Holili to Taveta : 7 hours 19 minutes

    Baseline: 2011

    After

    Holili to Taveta: 1 hour 41 minutes (76% reduction from baseline)

    Time & Traffic Survey: 2017

GALLERY

IMAGES
VIDEOS

CONTACT

LOCATION

The Taveta/Holili border crossing point between Southern Kenya and Northern Tanzania is located about 264 km SouthEast of Mombasa and 110 km West of Arusha. The Kenyan side of the border is in Taita-Taveta County, while the Tanzanian side is in Himo Town, Rombo District, Kilimanjaro Region. Taveta is one of the key border crossing points between the two countries due to the border’s proximity to major cities.

WHY

To transport goods to Arusha and surrounds in northern Tanzania, vehicles currently must pass through the Namanga border. This route is considerably longer than the Taveta/Holili route. Operationalising the Taveta/Holili border is expected to increase with the construction of a new Voi-Arusha road passing through the two border points, stretching the capacity of the current infrastructure and operations and increase waiting time for import and export processing. Increased delays create costs for traders.

  • IMPLEMENTING PARTNER

    Tanzania Revenue Authority

  • RESULTS

    Baseline Data

    Taveta to Holili: 22 hours 59 minutes

    Baseline: 2011

    After

    Taveta to Holili: 2 hours 55 minutes ( 87% reduction from baseline)

    Time & Traffic Survey: 2017